07 January 2026

October/November 2025

  • fan coils functional as of 10/10/25
  • endesa moved meter outside 25/9/25
  • old electricity gubbins removed from front wall 21/10/25 and wall lime rendered
  • tiling of vault completed mostly by Hasan, bit over well by JSD/JAC(mostly)
  • wood behind bakerlite light switches 
  • partition wall in 'Emma's bedroom' ensuite installed and painted
  • Under-stairs shower room on ground floor painted / tiled. Shower not installed

  • ceiling of living room taped/filled by plasterer (who no-showed and thus the ceiling needs second coat)

  • high parts of ceiling of 4th bedroom taped/filled by JAC whilst accessible
  • timber from BigMat for joists of upstairs hall ceiling / new loft floor
  • 30? boards delivered by Marc Salabert 4/11/25 for upstairs stud work
  • wall between 4th bedroom ensuite/hall built by Hasan and rendered with concrete
  • existing wall between 4th bedroom/RoR removed
  • new wall with wardrobe between 4th bedroom and ensuite partially built by Hasan (not part with glass bricks)
  • 5 up/down lighters installed installed in upstairs hall
  • wall raggled for switch by front corner (bottom of where new stairs will go) 
  • New hall ceiling built
  • Stairs to loft removed