October/November 2025
- fan coils functional as of 10/10/25
- endesa moved meter outside 25/9/25
- old electricity gubbins removed from front wall 21/10/25 and wall lime rendered
- tiling of vault completed mostly by Hasan, bit over well by JSD/JAC(mostly)
- wood behind bakerlite light switches
- partition wall in 'Emma's bedroom' ensuite installed and painted
- Under-stairs shower room on ground floor painted / tiled. Shower not installed
ceiling of living room taped/filled by plasterer (who no-showed and thus the ceiling needs second coat)
- high parts of ceiling of 4th bedroom taped/filled by JAC whilst accessible
- timber from BigMat for joists of upstairs hall ceiling / new loft floor
- 30? boards delivered by Marc Salabert 4/11/25 for upstairs stud work
- wall between 4th bedroom ensuite/hall built by Hasan and rendered with concrete
- existing wall between 4th bedroom/RoR removed
- new wall with wardrobe between 4th bedroom and ensuite partially built by Hasan (not part with glass bricks)
- 5 up/down lighters installed installed in upstairs hall
- wall raggled for switch by front corner (bottom of where new stairs will go)
- New hall ceiling built
- Stairs to loft removed